How to Cast a Concrete Floor – Build-up, Materials and Quantities

A concrete floor is a solid and durable solution in a shed, an outbuilding, a garage or an annexe, for example. With good preparation you can easily cast the floor yourself – most of the important work is in the base, before any concrete goes in.

In this guide we go through the build-up layer by layer, the materials you need, how to cast and level the floor, and how to work out the quantities.

How to Cast a Concrete Floor – Build-up, Materials and Quantities - maxibag.dk

The build-up of a concrete floor

A concrete floor laid directly on the ground – also called a ground-bearing slab – typically consists of these layers, from the bottom up:

  1. A firm, load-bearing base free of topsoil and roots
  2. A capillary-breaking layer of at least 15 cm that stops moisture from the ground
  3. Insulation, if the room is to be heated
  4. Reinforced concrete, typically 10-12 cm

If the room is to be heated, the building regulations set requirements for the insulation, and the project may need a permit. Check the rules with your local authority before you start.

Excavation and base

Dig away all topsoil and roots until you reach firm, undisturbed ground. Topsoil settles and rots, so it must never be left under a floor. The depth depends on how high the floor needs to be, but allow at least 30-40 cm below the finished floor.

Where you need to build up, use road base in layers of no more than 15-20 cm, and compact each layer thoroughly with a plate compactor.

Capillary-breaking layer and insulation

Ground moisture rises through dense materials like water through a piece of kitchen roll. A capillary-breaking layer of coarse, even grains stops it and keeps the floor dry. The layer must be at least 15 cm thick.

Leca® 10-20 Coated is particularly suitable, as coated Leca balls are both capillary-breaking and insulating and do not absorb water. For a heated room you will usually also need insulation on top, in the thickness required by the building regulations.

Level the layer so it is completely flat before you move on.

Formwork and reinforcement

Set up formwork along the edges if the floor is not cast between existing walls. Use a spirit level or a rotating laser to set the top edge at the right height – it becomes your guide when you level the concrete.

Lay reinforcement mesh over the whole area so the sheets overlap. Raise the mesh on spacers so it sits in the middle of the concrete rather than on the base. The reinforcement helps prevent cracks and makes the floor stronger.

Choose the right concrete

For a floor in a dry, heated room, passive concrete is sufficient, while a garage floor should be cast in aggressive concrete, as the car brings in de-icing salt. An unheated shed or outbuilding is normally cast in moderate concrete. Read more in Concrete exposure classes – passive, moderate, aggressive or extra aggressive?

The easiest option is to order casting materials in the right exposure class, with the cement and aggregate measured out for the amount of finished concrete you need. See how to mix in Concrete mix ratio.

How to cast the floor

  1. Dampen the base lightly if it is very dry, so it does not draw water from the concrete.
  2. Mix and pour the concrete in sections, starting in the far corner so you work your way towards the door.
  3. Spread and compact the concrete with a shovel and a tamper or vibrator so there are no air pockets.
  4. Level it with a long, straight plank or screed board, pulled back and forth across the formwork.
  5. Float the surface with a float or trowel once the concrete has settled a little and is no longer shiny with water.

If you want an extra fine, smooth surface, you can finish with a thin top layer of cement and building sand.

Curing – give the concrete time

Concrete needs to cure slowly to become strong. Keep it moist for the first week by watering lightly or covering it with plastic, and protect it from direct sun, wind and frost. You can usually walk on the floor after a couple of days, but the concrete only reaches full strength after approx. 28 days. So wait before putting heavy loads on it, such as driving a car in.

How much do you need?

Example: A floor in an outbuilding of 3 × 5 metres = 15 m².

  • Concrete, 10 cm: 15 m² × 0.10 m = 1.5 m³ of finished concrete
  • Capillary-breaking layer, 15 cm: 15 m² × 0.15 m = 2.25 m³ = 2,250 litres

Add approx. 5-10% to the concrete, as the base is rarely perfectly level. You can use our quantity calculator for the other layers. We deliver throughout Denmark – see delivery and delivery methods, and remember to place the bulk bags on firm ground close to the site.